The encyclopedia · Engineering & Operations · Financial decision · 2013–2024
Jeddah Tower: six years stalled after the purge arrested its builder
Saudi Arabia's 1,000m Jeddah Tower stalled at 30% built when the 2017 purge arrested contractor Binladin Group's chairman; work only restarted in 2024.
Jeddah Economic Company · Saudi Binladin Group · Kingdom Holding · 2018-01
What happened
In 2009 Saudi Arabia announced the tower that would end Burj Khalifa's record: Jeddah Tower, designed by Adrian Smith and Gordon Gill to pass 1,000 metres, with 59 elevators and 12 escalators, at the heart of the multi-billion-dollar Jeddah Economic City. Construction began in 2013 with Saudi Binladin Group as main contractor — a builder with royal contracts going back decades, and a shareholder family at the centre of the project.
In November 2017 the kingdom's anti-corruption purge swept up the project's own inner circle: Prince Alwaleed bin Talal of Kingdom Holding, the tower's most famous backer, and Bakr bin Laden, chairman of the Binladin Group, were arrested. Construction halted in early 2018 with the tower roughly 30% built. In March 2018 the state said Bin Laden's 36.2% stake in the group would be transferred to the government after he was charged with corruption; he was released in 2019 after reaching a settlement.
The stall became the story. For six years the world's would-be tallest building stood as a concrete stump, Burj Khalifa kept its record, and the developer's only move was to find a new builder. In 2024 Jeddah Economic Company removed Binladin Group from the project and chose a consortium of El Seif Engineering Contracting and China State Construction Engineering Corp to finish the remaining 70%.
Construction restarted in late 2024, and by December 2025 the tower had passed 80 floors, with completion targeted for 2028. But the gap was real: more than half a decade in which the money sat frozen, the momentum died and the record chase stalled — all because the world's tallest project had been handed to one contractor whose standing with the state was about to collapse.
Why it happened
- One contractor held the whole bet. When the purge arrested its chairman, the project stopped mid-air — the world's tallest building had no second builder lined up.
- The owners were inside the state. The purge reached the project's own backers — Alwaleed arrested, Bin Laden's stake seized — so the developer could not shield its contractor or stay above politics.
- No plan for a stalled giant. Replacing the contractor took six years — Jeddah Economic Company chose the El Seif–CSCEC consortium only in 2024, leaving a third-built tower in the sun.
- Ambition outran resilience. A 1km tower was built as a single point of failure: one family's contractor, one royal patron, one purge away from freezing.
The lesson
A megaproject is only as strong as its least independent link. Jeddah Tower bet the world's tallest record on a contractor whose fate lay with the state, and one purge froze the site for six years.
Sources
- Construction Week — KHL, Jeddah Tower: contractor switch and six-year halt (24 May 2024: work began 2013 with Saudi Binladin Group as main contractor; construction halted in January 2018 at about 30% complete; Bakr bin Laden among dozens held in the November 2017 corruption crackdown; in March 2018 the state said his 36.2% stake in the group would transfer to the government after he was charged with corruption; released 2019 after a settlement; Prince Alwaleed of Kingdom Holding also held and freed; 2024: Jeddah Economic Company chose El Seif Engineering Contracting and China State Construction Engineering Corp as the new main contractor, removing Saudi Binladin Group from the project)
- The News — Jeddah Tower surpasses 80 floors (11 Jan 2026: tower passed the 80-floor mark in December 2025 per Thornton Tomasetti data; designed to stretch over 1,000 metres and 57 million sq ft; completion expected 2028 as part of Saudi Arabia's diversification push)
spotted an error? The club wants to know.
More like this
Arabtec built the Burj Khalifa, then lost $626M in a year and went bankrupt
Dubai World owed $59B, asked for a standstill, and rattled global markets
Berlin's new airport opened 9 years late at triple the budget — undone by its fire system
Somewhere, someone solved the problem this company failed at. 2nd Opinion →

Comments · 0
Sign in to join the comments.