The encyclopedia · Engineering & Operations · Operational decision · 2009
Boeing outsourced 70% of the 787 Dreamliner — and lost control of its own airplane
Boeing outsourced most of the 787 to global suppliers to cut costs. The result: years of delays, $32B in cost overruns, and quality problems that persist.
Boeing · 2009
What happened
When Boeing designed the 787 Dreamliner, it made a radical decision: outsource roughly 70% of the aircraft's design and manufacturing to a global network of suppliers. Partners in Japan, Italy, South Korea and elsewhere would build major sections, and Boeing would do final assembly. The goal was to cut costs, share risk and accelerate development.
The result was the opposite. Suppliers struggled with coordination, quality varied, and sections arrived at Boeing's Everett factory with missing parts and misaligned fittings. The 787 was delivered over three years late, with cost overruns estimated at $32 billion. Boeing had to send engineers to supplier sites worldwide to fix problems that should have been caught earlier.
The 787 eventually became a commercial success, but the outsourcing model damaged Boeing's engineering culture and institutional knowledge. The case is now cited alongside the 737 MAX crisis as evidence that Boeing's shift from an engineering company to a financial company — optimizing for cost and shareholder returns over technical mastery — had systemic consequences.
Why it happened
- Boeing outsourced 70% of the 787 to cut costs and share risk, but lost control of quality and integration.
- Global suppliers struggled with coordination, and sections arrived with missing parts and misaligned fittings.
- The program was delivered over three years late with $32B in cost overruns.
- The outsourcing model eroded Boeing's internal engineering capability and institutional knowledge.
The lesson
You can outsource manufacturing, but not integration. When 70% of a complex product is built by others, the integrator must be stronger, not weaker.
Aftermath
The 787 became a commercial success with over 1,500 orders, but the program's cost overruns were never fully recovered. The outsourcing model's damage to Boeing's engineering culture is cited as a contributing factor to the later 737 MAX crisis.
Sources
- Boeing 787 Dreamliner — Wikipedia (development, outsourcing, delays)
- Forbes, 12 February 2024 — Boeing Is Haunted By Two Decades Of Outsourcing (Boeing outsourced 70% of the 787's design, engineering and manufacturing to over 50 strategic partners; loss of supplier coordination and control)
spotted an error? The club wants to know.
More like this
Boeing's 737 MAX had a hidden flight-control flaw that killed 346 people in two crashes
Boeing took a fixed-price deal to build Air Force One — it has eaten $3B in losses
Boeing's Starliner went up for eight days — it came home empty, nine months later
Somewhere, someone solved the problem this company failed at. 2nd Opinion →

Comments · 0
Sign in to join the comments.