In September 2021 Egypt's National Authority for Tunnels signed a $4.45bn contract with a consortium of Siemens Mobility, Orascom Construction and Arab Contractors for a 660km electrified line linking the Red Sea port of Ain Sokhna with Alexandria and Marsa Matrouh — a link Siemens branded a 'Suez Canal on rails'. Siemens' share was about $3bn, and the company said its trains would be delivered by the end of 2023, with the order to be completed by 2027 and the main line designed for more than 30 million passengers a year.

The scope grew before the first milestone arrived: in May 2022 Siemens announced an €8bn framework for a 2,000km network with 41 high-speed, 94 regional and 41 freight trains, which CEO Roland Busch billed as the world's sixth-largest high-speed rail system. Then the headline date slipped: the end-2023 train handover passed, and the first phase's pilot operation was only launched on November 9, 2025, when Prime Minister Mostafa Madbouly marked the moment at the TransMEA exhibition in Cairo beside the network's first eight-car Velaro.

The gap between the podium and the pilot — roughly two years on the train commitment, passenger service still to come — is the case's core cost. On a desert main line, dates quoted at signing become public scoreboards, and every month they slip compounds the credibility discount on the rest of the 2,000km programme.

Siemens trains were promised by end-2023; the first entered pilot operation in Nov 2025 — about two years late, with passenger service still pending.

The contract pledged Siemens train delivery by end-2023 — a date fixed less than two years into a programme whose civil works, systems integration and financing were still unproven.

Within eight months the deal had expanded into an €8bn, 2,000km framework with 176 trains and eight depots, multiplying programme complexity before the first line had proved its schedule.

Long-lead items dominate desert rail: rolling stock, signalling and depots at this scale cannot be compressed to fit a signing-ceremony date.

A delivery date set at a signing ceremony becomes a political meter: end-2023 train pledges for a 660km desert line bought a two-year wait for the pilot run. Schedule by physics, not podiums.

Pilot operation of the first phase began on November 9, 2025, with Madbouly and Busch marking the launch at TransMEA 2025; the eight-car, 479-seat train they inspected was the network's first. Passenger service on the Ain Sokhna–Alamein–Matrouh line and the remaining phases of the 2,000km programme still lie ahead, against an original contract that envisaged completing the first order by 2027.

FOLLOW THE EVIDENCE

The sources

  1. 'Suez Canal on rails' - Egypt signs $4.5 bln high-speed rail deal reuters.com
  2. Egypt signs €8 billion deal with Siemens for high-speed rail dw.com
  3. Madbouly launches pilot phase of Egypt's High-Speed Rail at TransMEA 2025 dailynewsegypt.com