Areva was the spearhead of France's nuclear industry: state-owned to 87%, it mined uranium, made fuel, built reactors and recycled spent fuel as one integrated group. The model was sized for a nuclear renaissance that never came. It paid €1.8bn for the Canadian miner UraMin in 2007 and €1.25bn developing its Namibian deposits — then discovered the ore was far poorer than expected, burning about €3bn. Its fixed-price Olkiluoto 3 reactor, promised for 2009, slid to 2018, with penalties a Le Figaro estimate put at €4–4.5bn.

Fukushima in March 2011 froze new-build plans worldwide — and Areva had already lost the $20bn-plus Abu Dhabi tender to South Korea in 2009. It made a loss every year from 2011. In November 2014 it issued its third profit warning in four months, dropped its 2015–16 targets, and watched the shares open 23% lower; S&P cut the debt to speculative grade and analysts said the group needed a €1–2bn capital injection. Economy Minister Emmanuel Macron insisted 'Areva is here to stay.'

The reckoning came in February 2015: a provisional 2014 net loss of €4.9bn — larger than the group's €3.7bn stock-market value and about three-quarters of its equity — including new Olkiluoto provisions, the Comurhex II uranium plant write-down and end-of-cycle fuel obligations. The final figure, published on 4 March by the new Varin–Knoche leadership, was €4.8bn on revenue down 8% to €8.3bn, with €5.8bn of debt, €720m of extra Olkiluoto charges, and no free cash expected before 2018.

The state had no choice but surgery: a €1bn cost-cutting plan and up to €1bn of asset sales in March 2015 — the Canberra instruments unit already lined up — and a refusal to play 'architect-ensemblier' on solo turnkey projects. As one senior industry source told Reuters in 2014, each piece cut loose would be too small to compete; the group could no longer afford to stay whole either.

2014 net loss €4.8bn — larger than the group's €3.7bn market value; shares halved in 2014; S&P cut the debt to speculative grade

Fixed-price turnkey reactor contracts turned every delay into Areva's liability; Olkiluoto 3 alone was re-provisioned year after year, €720m more in the 2014 accounts.

The 2007 UraMin acquisition — €1.8bn plus €1.25bn of development — was written off when the Namibian ore proved far poorer than expected.

Fukushima froze the export market the integrated model was sized for; Abu Dhabi had already gone to Korea with a $20bn-plus order.

Capital projects like Comurhex II were financed against renaissance demand, so the 2014 cleanup hit deferred taxes, plants and contracts all at once.

A single-technology champion has no cycle to hide in. When its fixed-price projects and renaissance bets fail together, the write-off can dwarf the market cap.

The 2015 net loss came in at €2bn as restructuring itself cost money, and by February 2016 the government was negotiating extra months of delay on Areva's bank repayments; RTL reported the state rescue would be largely at taxpayers' expense, several billions of euros. EDF was set to become majority shareholder of the reactor business, ending a decade of infighting between the two state groups that had crystallised in the Lauvergeon–Proglio feud. The complete nuclear company ended the decade smaller, dismantled, and publicly owned.

FOLLOW THE EVIDENCE

The sources

  1. Areva rethinks strategy after ditching targets web.archive.org
  2. Nucléaire: Areva chiffre de manière provisoire ses pertes 2014 à 4,9 milliards d'euros 20minutes.fr
  3. Areva annonce un plan d'un milliard d'euros d'économies à l'horizon 2017 lemonde.fr
  4. Nucléaire : les 4 affaires qui ont plombé Areva rtl.fr